Eramet starts DLE lithium production in Argentina

Eramet starts DLE lithium production in Argentina, targets 4–7kt LCE in 2025 and 24kt/y at Centenario.
0
Eramet starts DLE lithium production in Argentina
Eramet

Eramet starts DLE lithium production in Argentina and reports stable unit performance. The Centenario project reached industrial operation in June. Eramet starts DLE lithium production in Argentina to lift near-term LCE output. The company targets 4,000–7,000t in 2025 and 24,000 t/yr at nameplate.

Commissioning progress, volumes, and customers

Eramet starts DLE lithium production in Argentina through its Eramine Sudamerica JV with Tsingshan. The DLE units operated near nominal yield and throughput, the firm said. Centenario produced 710t LCE in the first half after earlier evaporation issues. However, Eramet fixed the brine concentrating equipment and restored normal operations. The company sold 520t of industrial and technical grade LCE. Most sales went to Chinese cathode active materials manufacturers.

2025 guidance and financial context

Eramet expects Centenario to deliver 4,000–7,000t LCE in 2025. The site plans a gradual ramp toward 24,000 t/yr capacity. Meanwhile, Eramine Sudamerica posted a €37mn loss in January–June. As a result, execution discipline and uptime remain critical to hit guidance. Direct lithium extraction and evaporation now run as integrated flowsheets.

The Metalnomist Commentary

Eramet’s milestone validates a second industrial DLE reference in the Lithium Triangle. Consistent brine pre-treatment and evaporation stability will determine the pace to 24kt/y. Watch impurity control and customer qualification, which shape pricing and cash flow through 2025.